15 Army Installation Assessments – USACE Ft. Worth District

In the fall of 2022, Leisnoi-KEMRON JV was awarded two projects through the USACE Fort Worth District to provide Programmatic Environmental Assessments (PEA) at 15 Army installations to support decisions on locating future weapons systems.

The PEAs will be performed pursuant to the National Environmental Policy Act and will include an analysis of baseline cultural and natural resources conditions and an evaluation of any environmental impacts.

Thank you to Edwards-Pitman, who will be our primary subcontractor.

Wetland Delineation and Permitting

KEMRON Environmental Services, Inc. (KEMRON) was retained to delineate wetlands on the Gwinnett County Regional Airport property. The county was proposing to construct a new taxiway and associated airport facilities. The project involved delineating all wetlands within the construction site, reconnaissance of additional wetlands on the airport property, performing a protected species survey and preparation of a report for the Airport Authority and the Gwinnett County Department of Transportation that included permitting options, preparation of the ecological and wetland sections of an Environmental Assessment that was submitted to the Federal Aviation Administration, and preparation and submittal of a federal wetland permit. In addition to preparing the reports, KEMRON attended several meetings with county officials, USACE personnel, and/or concerned citizens to explain the permitting process, anticipated impacts to the wetlands and streams, and the activities to minimize impacts to the environment.

return to previous page

Harbins Park Soil Bioengineering Project

KEMRON was tasked with the Harbins Park Soil Bioengineering Project in Lawrenceville, GA for the implementation of the restoration and repair specifications within a 1200-acre recreation and conservation park. Harbins Park experienced significant erosion damage due to vehicle use as well as bank failure and erosion along two surface water systems intersecting the park.

harbins_park

Historical use of the property by four-wheel drive and ATV operators created severe erosion damage throughout the park. Erosion damage included channels up to four feet deep extending over hundreds of feet in length. Site preparation involved mobilizing site support facilities, temporary utilities and the creation of an approved construction entrance with appropriate sediment management controls. An equipment and materials storage area was constructed. Following mobilization, contractor progress meetings were held prior to initiation of each major construction event. The construction was based on a contractual specifications and drawings package establishing minimum design and construction criteria. Using the conceptual level guidance and minimum design criteria, KEMRON was required to build the environmental controls to best suit the specific environmental constraints. Thus, the specifications and drawings provided the performance objectives with KEMRON providing the final environmental control structures, stream bank repair and reconstruction and site restoration to a natural structure and vegetative setting.

KEMRON repaired 10 acres of damaged areas over a two-mile access road. Mitigative measures included the placement of a straw substrate, construction of 20,000 sq ft of Core Mat erosion matting, and strategic placement of natural log diversions on all sloped areas. Once erosion repairs were complete, KEMRON completed site restoration activities at the site by re-planting with an indigenous seed mix returning the area to a natural grassy setting.

Two small rivers with relatively shear banks and seasonal high water scouring damage and bank failure intersect the park. KEMRON was tasked with reducing the impacted bank slopes to less than a 2 to 1 slope. Once the earthwork was complete, KEMRON planted 6000 tubling plantings of four indigenous woodland plant types. The combined earthwork and replanting effort provided the necessary bank stabilization to allow the stream banks to return to a natural condition while reducing erosion and bank failure into the streams. The lower reaches of the stream slopes were further armored with Type III riprap from the high water mark to the bottom of the stream channel. Another damaged area approximately 1000 ft long and 80 ft wide required a series of riprap check dam flow reduction zones. These check dams were installed through the placement of more than 1000 tons of riprap.

This project was completed ahead of schedule and on budget under a fast paced, two-month field schedule to meet the optimum winter to spring dormant planting season. All work was completed in coordination with the client’s bioengineering design team and KEMRON’s certified horticulturist under strict quality controls for seeding, fertilizing and core mat placement. Conservation protection mechanisms such as silt fence sediment controls, temporary and permanent seeding, tree protection and fencing were implemented to protect the local environment. KEMRON regraded over 10 acres of damaged area in order to repair major surface erosion damage. All soils were re-used, regraded and revegetated with indigenous common grasses and wildflowers. The projects scope of work was specifically the installation of sediment controls and revegetation in an effort to control future soil migration.

KEMRON provided site monitoring and maintenance to include watering, inspection and minor repair to drainage structures and site security to minimize trespass. KEMRON was responsible for plant warrantees and compliance inspections throughout the maintenance period.

return to previous page

Dobbins Air Reserve Base

KEMRON Environmental Services, Inc. (KEMRON) was contracted to perform a NEPA Environmental Assessment (EA) at Dobbins ARB in Marietta, GA under a contract to the Georgia Department of Defense. The EA was prepared in accordance with the applicable guidelines and recommendations set forth by the DOD and satisfied the criteria of the federal, state, and Army regulations and the intent of NEPA. The intent was to establish existing baseline environmental conditions at the site and how ARB training activities impact those conditions. Alternatives to the current activities were also identified.

Investigations of the properties included the following: past and present land uses, site improvements, activities conducted on the premises, existing natural conditions, impacts of the activities on the environment, alternatives to the present activities, measures of impact mitigation, and the presence or potential for site contamination. KEMRON identified conditions indicative of special resource value for the property such as natural, historic, cultural, recreational or scientific; the presence of potential jurisdictional wetlands; the presence of protected plant and animal species; and areas of potential archaeological, cultural or historical significance. The premise was also investigated for the potential for site contamination from the presence of hazardous materials.

return to previous page